The Knight Street Bridge overnight pavement rehabilitation work will continue until the end of October. The public can expect nightly single-lane closures (weather permitting) on the bridge from 9 pm to 5:00 am on weeknights (until 9:00 am on weekends) – at least one lane will always be open to traffic during this work. Please note there is a width restriction of 3.8 metres for commercial vehicles.
As part of TransLink’s Maintenance and Upgrade Program, rehabilitation to the deteriorating components of the Knight Street Bridge will occur through December 2023. More than 100,000 vehicles cross Knight Street Bridge on an average day and, at 49 years old, maintenance is critical to ensuring the safety and reliability of this crossing for all bridge users. This work includes deck bearing replacement, deck resurfacing, and cycling/pedestrian railing replacement.
Construction Information
Pavement rehabilitation work is expected to be completed by late October 2023.
- Single-lane closures in both directions (weather permitting) starting May 3
- Weekdays from 9:00 p.m. to 5:00 a.m.
- Weekends and statutory holidays from 9:00 p.m. to 9:00 a.m.
- Width restriction of 3.8 metres for commercial vehicles
Some of the pavement rehabilitation work will require intermittent ramp closures at the Marine Drive and Mitchell Island interchanges.
- This work is expected later in May from 9:00 p.m. to 5:00 a.m. (exact dates TBD)
- Access to Mitchell Island will be provided at all times, but the public may need to detour and use the ramps of the opposite direction for access.
- Every effort will be made to minimize the duration of any ramp closures during this period.