People travelling in the evenings along the Malahat section of Highway 1 near the Tunnel Hill project north of Victoria can expect delays as the project moves toward completion.

Beginning on Monday, Sept. 11, 2023, single-lane-alternating traffic will be in place overnight from 8 p.m. until 6 a.m. This work is expected to take place four to five nights each week, including some Sunday nights, weather-dependent, until the project is complete this fall.

Travellers should expect delays of as much as 20 minutes through the site during the overnight work.

In addition, short traffic stoppages may occur during the daytime for the contractor to safely mobilize and demobilize personnel and equipment.

This work marks the final phase of repairs at the Tunnel Hill site, which was washed out during the atmospheric river flood in November 2021.

Drivers are reminded to drive according to conditions and observe traffic-management personnel and signage in the area. For up-to-date information about road conditions, visit: http://www.drivebc.ca/

Feature Image
Newsletter Issue
Weight
0
Section
feature on advocacy and policy
No
Featured post
No
Publish on homepage
Off
Feature on "Incase You Missed It" Section of The Bulletin
Off